The vent was not negotiable

A 1.6 m smoke extract opening is sized by the fire engineer, not by the interior designer. It cannot be covered, it cannot be reduced, and it cannot have anything hanging in the extract path. What it can have is a screen around it.

A ring from 1.6 m inner diameter to 4.2 m outer diameter is 11.84 m² of surface — small, as screens go, and about 10 cabinets. That is a modest amount of hardware for something that becomes the ceiling feature of the whole atrium, which is exactly why rings get built.

The constraint that mattered was the 60 mm clearance from the vent frame. That is not a design preference; it is the space the fire damper needs to swing. Everything about the inner edge of the screen follows from those 60 mm.

A ring is not a rectangle with a hole

Feed a normal 16:9 video into a ring and you get a letterboxed strip that runs around the circumference and leaves the inner third empty. Feed it a mapped file and it still will not work, because the pixel addresses on a ring are polar: the same content is stretched at the outer edge and compressed at the inner edge, and the ratio between them here is 2.6 to 1.

So the mapping is done in polar coordinates. The media server renders a 3,600 × 300 canvas — 3,600 pixels around the circumference at P2.5, 300 across the radial width — and a shader converts each output pixel to its radius and angle. Content authored as a flat ring texture plays correctly; a normal video has to be warped into that texture first.

We supply the mapping project file, not just the screen. Without it the client has a beautiful object that can only show a test pattern.

On site, before the shell closes: the ring base sits on the concrete upstand and the cabinets go up through the void. There is no ceiling platform to work from, which is why each one had to stay under 20 kg.
On site, before the shell closes: the ring base sits on the concrete upstand and the cabinets go up through the void. There is no ceiling platform to work from, which is why each one had to stay under 20 kg.

Ten cabinets, all curved on two axes

The ring's surface is not cylindrical. It curves in the radial direction, following a shallow cone that drops 180 mm from outer edge to inner, and it curves around the circumference. Each cabinet is cut on both, which means the modules are trapezoids, not rectangles.

Ten cabinets at this size means each one is roughly 1.2 m² and about 17 kg. That is light enough for two people to lift into place on a scissor lift, which matters because the atrium has no ceiling access platform and everything went up through the void.

The joints between cabinets run radially, like spokes. Get the first one wrong and the error accumulates around the circle until the last joint does not close. We set the first cabinet off a laser line, then worked both directions and closed the ring at the point furthest from the start, trimming the final joint on site. The gap there is 1.5 mm and it is the only joint that is not nominal.

Same construction, a different ring: assembled on the test frame in the workshop and run continuously for three days before packing. The opening stays open on site too — the screen is built around the void rather than across it.
Same construction, a different ring: assembled on the test frame in the workshop and run continuously for three days before packing. The opening stays open on site too — the screen is built around the void rather than across it.

Light spill on a ceiling

A ceiling screen lights the room. On a 4.2 m ring at 600 nits, the floor 9 m below gets measurable light, and the surrounding ceiling — which on this project is a dark grey spray finish — gets a lot more. The first mock-up made the whole ceiling glow and the ring disappeared.

Two fixes: a 45 mm baffle around the outer edge, angled away from the ceiling, and content that keeps the outer 8% of the radial width dark. The baffle alone got most of it. The dark border is insurance, and it also frames the ring so it reads as an object rather than a hole in the light.

Power is 9.5 kW at full white, which the existing lighting circuit could not take. We ran a new feed from the floor's distribution board — 60 m of cable and a new 32 A breaker, which is not glamorous work and is always underestimated in the budget.

What we would change

The fire damper inspection. We built the ring to 60 mm clearance and then the fire contractor tested the damper and found it swings 85 mm, not 60. The inner trim came off, the first row of modules came out, and we moved the whole inner edge back by 30 mm over two nights. The screen still works. The lesson is to watch the damper move before drawing anything.

Second: the ring has no rear access. It is front-service, which is fine, but the inner edge is 1.6 m from the centre and a technician on a lift cannot easily reach the last 200 mm of the inner band without leaning into the vent opening, which the fire officer will not allow. On the next one we put a 300 mm maintenance ring inside the screen line, black, so there is somewhere to stand.