What the ceiling actually looked like

The atrium is four storeys deep. The slab above it is bare concrete with a sprinkler main running across, a smoke curtain track, and the six chandeliers hanging on their own independent cables from cast-in anchors. Ceiling height under the slab is 9.4 m; the lowest chandelier hangs to 6.8 m.

That number decided the dome. A 6 m base with a 1.2 m rise puts the crown at 7.6 m and the rim at 8.8 m, which clears the chandeliers by 800 mm at the lowest point and leaves room for a technician to get a hand in. Push the rise to 1.5 m and the crown drops to 7.4 m, and suddenly the crown band is inside the chandelier canopy. Push it the other way to 900 mm and the dome goes flat enough that the top three bands read as a ceiling, not a sphere.

So the rise was not a design choice. It was the gap between a chandelier and a slab.

Twenty-eight cabinets, four of them one-offs

A 6 m base at 1.2 m rise gives a 4,350 mm radius and 32.8 m² of surface. At P2.5 that is 5.25 million lit pixels on a media canvas of 7,540 × 2,647 — two different numbers, and the client's AV team needed both: the first for the processor, the second for whoever was going to render content.

The shell breaks into 28 cabinets. Sixteen of them are the standard 640 × 480 curved module, cut on the 4,350 mm radius. Eight are the narrow rim band, where the surface is almost vertical and the module has to be trimmed to a trapezoid. The remaining four are the crown ring, and those are one-offs — each one is a different shape because each sits at a different latitude, and the pixel pitch across the crown compresses as the surface turns horizontal.

That is the part people underestimate on a dome. On a flat wall every cabinet is the same. Here, four out of twenty-eight had to be drawn, cut and wired individually, and they are the four that sit directly above the escalators.

The same shell from below, three rows in. The chandelier cut-outs are framed in steel before the modules go on, not after.
The same shell from below, three rows in. The chandelier cut-outs are framed in steel before the modules go on, not after.

The chandeliers had to be cut in, not covered

Six chandeliers, six holes. Each one gets a steel ring welded into the meridian framework, the modules around it cut back to the new edge, and the pixel map regenerated so the content flows around the opening instead of disappearing behind a disc.

We have seen the other approach: build the dome solid, then screw a black plate over the hole. It works for a week. Then the plate collects dust, the edge catches the light from the screen, and from the ground floor it reads as a patch on an otherwise clean surface. On a four-storey atrium, everybody sees it.

The rings went in at frame stage, before any module. That meant the chandelier contractor and our welder were on the same scaffold for two days, which is the sort of coordination that only happens if somebody puts it in the schedule instead of assuming it will sort itself out.

Eleven lifts, no closed days

The mall opens at 10:00 and closes at 22:00. Our window was 22:30 to 06:00, and the atrium could not have scaffolding standing in it when the doors opened. So the shell went up in eleven sections, each one pre-assembled on the floor of the loading bay, lifted through the service shaft, and bolted to the previous section before the shift ended.

A section is roughly 3 m² and 40 kg of frame. Eleven lifts, eleven nights, then three more nights for modules and two for commissioning. The mall never lost a trading hour, and the only visible trace in the morning was a scissor lift parked in a corner.

The cost of doing it this way is real: eleven set-ups instead of one, and every set-up needs its own alignment check against the section before it. We budget about 15% more labour for a night-shift dome in a live building, and we say so in the quote rather than discovering it later.

What we would change

Two things. First, the smoke curtain track ran 40 mm lower than the ceiling plan showed, and we found it on the second night. Nothing broke, but two rim cabinets had to be re-cut with a notch that is now hidden behind a trim. A laser scan of the slab would have cost a day and saved four.

Second, the content. The mall's agency delivered a 16:9 loop three days before commissioning, and on a dome that either wraps into a band around the rim or leaves the crown black. We ended up pre-rendering a dome master from their footage ourselves, which is work we are happy to do but it should have been in the schedule from week one.